A Few Of Our Projects
City of Duncan – Pine Ave Utility and Streetscape
Upgrade Project Duncan, BC
Leuco Construction was the Prime Contractor for water, storm, sanitary, and streetscape upgrades for a residential road in Duncan, BC. Working closely with the City of Duncan and residents, we were able to provide service upgrades and transportation improvements to the community. Works were coordinated to ensure residents maintained access to their homes and experienced minimal disruption to their water and sanitary services. The project included deep trench work and shallow grade gravity mains. Streetscape improvements included new concrete curb and gutter, sidewalks, and streetlighting.
City of Prince Rupert
Beach Place Storm and Sewer Replacement
Alberni Clayoquot Regional District
Walker Road Watermain Replacement
HWY 19A Culvert Relining
The work consists of installing a 30m 600mm culvert under the highway through an existing deteriorated csp culvert, replacement of manhole and injection of 10 cubic meters of grout encasing and filling the cavity between culverts. All on the beach and in the snow!
Museum Way Rehab
The work consisted of removal of approximately 320m2 of the existing cobblestones and road gravels. Salvaged cobblestones were packaged and delivered to the City’s public works yard.
Once the cobblestones and road structure were removed, the membrane on structure was cleaned for inspection by the Engineer; and required membrane on structure was repaired.
Once the membrane was accepted by the Engineer, drainage was installed prior to installation of new road structure and reinforced stamped concrete.
New Cross Pacific Undersea Fiber Optic Cable
The work consisted of pulling the cable ashore through a 1.25 km long HDD bore pipe with a 3.75 inch inside diameter using a winch on the beach.
The Cable ship was positioned offshore approximately 1.35 km in sufficient water depth. Once installed into the Beach Man Hole, Armor clamp installation, Split pipe installation from HDD entry pit to BMH, burial on the beach and from the end of the HDD to ships plow down position and restoration of the landing site took place.
Then 6 km of Fiber Optic Cable and power was installed through ducting and manholes from the BMH to the CLS. This was followed up by the installation of ducting, cable and construction of the OGB (Ocean Ground Bed).
Recirculating Water Feature Wall
After installation of the concrete and reinforcing steel the forms were stripped and the site was backfilled. Then the framing and underground utilities were installed followed by a concrete scratch coat and the rock facing.
Port Way Trestle Bridge Repairs and Upgrades
Aggie Hall Parking Lot Expansion
Coldbox Builders – Poultry Plant Expansion Project
Mill Rd Storm Sewer Upgrades
Eaglecrest Watermain and Service Upgrades
Village of Cumberland – 2019 Road and Utility Works Cumberland, BC
Leuco Construction was the Prime Contractor for utility and roadworks upgrades for three residential roads in Cumberland, BC. Residents received upgrades to water, sewer, and storm utilities, and road restructuring and resurfacing. Working with the Village of Cumberland and residents we were able to complete the project swiftly with minimal disruptions to traffic, residential access, and utility services.
City of Nanaimo – CINNABAR VALLEY WATERMAIN
Leuco Construction is the Prime Contractor for the replacement of watermains on Turnabout View, Centennary Drive and Richardson Road with the installation of approximately 915 lineal metres of pipe, associated fittings and service connections plus related works. The Works also included the replacement of a PRV station at the intersection of Stacey Crescent & Cinnabar Drive.
Are you looking for proposals on upcoming civil construction and utility projects? Let us know